Consolidated Rental
Car Facility
Louis Armstrong New Orleans International
Airport,
Kenner, LA
Original Start Date: February 2001
Second Startup Date: July 2008
Estimated Construction Completion: December 2013
Subconsultant to Coover-Clark & Associates (architect)
Project Cost: $70 million
-
Civil and structural
engineering design, development of plans and
specifications, and construction administration
-
Redevelopment of about 40 acres of property
into a consolidated location to better manage
car rental operations.
-
Demolition of existing buildings and site
infrastructure, constructing new buildings, site
paving, and infrastructure. Buildings included a
multi-story parking garage (not designed by Julien), a Customer Service Building, and more
than dozen individual structures to support
vehicle maintenance. The project also includes a
water tank, water well, and replacement utility
building as well as new stormwater drainage,
sanitary sewerage, and water supply
infrastructure.

-
The most challenging aspect of
the project was the difficulty in designing
infrastructure improvements with limited
information on prior subsurface conditions. Julien Engineering performed civil and
structural engineering design.
Ground Transportation
Consulting Services
Louis Armstrong New Orleans International
Airport,
Kenner, LA
Task assignments performed since 1997 for
various transportation improvements on an
as-needed/on-call basis
Subconsultant to Urban Systems, Inc.
-
Civil Engineering design and development of plans and
specs for various ground transportation
improvements
-
Roadway
pavement, signage, signalization, pedestrian
walkways, etc.
Rehabilitation of Taxiway
Sierra and Runway I-19
Louis Armstrong New Orleans International
Airport,
Kenner, LA
Design: 2001 Construction
completion: 2003
Subconsultant to W. O. Johnson & Associates
-
Civil Engineering design,
development of plans and specifications, and
construction administration
-
Assessment of pavement of
active taxiway and runway
-
Concrete sampling (coring),
analysis, and testing
-
Repair, replacement and
overlay of asphaltic and portland cement
concrete pavement
Airport Canal Closure
(Airfield Safety Improvements)
Louis Armstrong New Orleans International
Airport,
Kenner, LA
Design: 2003 Construction completion: 2005

Subconsultant to Pepper & Associates
-
Civil and structural
engineering design, development of plans and
specifications, and construction administration
-
Assessment of open canal
structures
-
Stormwater drainage analysis
-
Structural design for box
culverts and other drainage structures
New Parking Garage
Louis Armstrong New Orleans International
Airport,
Kenner, LA
Design: 2001
Construction completion: 2003
Subconsultant to Walker Parking Consultants,
Tampa, FL
-
Civil Engineering design,
development of plans and specifications, and construction
administration
-
New multi-level parking
garage and associated ground surface parking lot,
driveways, and sitework
-
Roadway realignment and
reconstruction, water supply lines and appurtenances, subsurface drainage structures,
sewer lines and appurtenances, adjacent ground
surface parking lot
Continental Presidents Club,
Concourse C,
Louis Armstrong New Orleans International
Airport,
Kenner, LA
Design: 1999
Construction completion: on hold
Subconsultant to Spencer Partnership Architects
-
Civil engineering design
and development of plans and specifications
-
New two-story addition to an existing concourse
-
Site survey, drainage,
water connections; reinforced concrete pavement
-
Repair, replacement and
overlay of asphaltic and portland cement
concrete pavement
Intersection of Airline
Highway & Cargo Road,
Louis Armstrong New Orleans International
Airport,
Kenner, LA
Design: 2001
Construction Completed: 2002
Subconsultant to Urban Systems, Inc.
-
Civil Engineering design
and development of plans and specifications
-
Reconfigure and signalize
existing state highway intersection, new roadway pavement, signage,
signalization, etc.
Lower
Roadway Improvements, Louis Armstrong
New Orleans International Airport
Rental
Car Shuttle Bus Planning, Louis
Armstrong New Orleans International Airport
Airport
Signage Inventory & Planning, Louis
Armstrong New Orleans International Airport
Strategic
Master Plan - Louis Armstrong New
Orleans International Airport
Reroofing
of the DHL/Airborne Express Cargo Hangar
- Louis Armstrong New Orleans International
Airport
MSY
Hurricane Civil/Structural Damage
Assessments - Louis Armstrong New
Orleans International Airport